NextDecade expects first LNG from Rio Grande Train 1 in H1 2027

PUBT·05/01/2026 12:01:07
Listen to the news
NextDecade expects first LNG from Rio Grande Train 1 in H1 2027
  • NextDecade reaffirmed timeline for Rio Grande LNG, targeting first gas in H2 2026, first LNG production in H1 2027.
  • Reported Phase 1 completion for Trains 1-2 plus common facilities at 67.8%, including engineering 98.4% plus procurement 94.3%.
  • Updated Train 3 completion at 44.2%, including engineering 91.4% plus procurement 82.6%.
  • Disclosed early cargo marketing progress, signing February 2026 FOB LNG sales for over 175 TBtu with expected cargo margin over $3 per MMBtu.
  • Stated contracted early-sales volume covers 33% of expected portfolio volumes from 2027 through early 2029.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. NextDecade Corporation published the original content used to generate this news brief via Business Wire (Ref. ID: 20260501318566) on May 01, 2026, and is solely responsible for the information contained therein.